Hi Everyone,
Not sure if this can be done but any help appreciated. I have a task that
lasts for 218 days with a contingency of 23 days (total 241 days). I would
like to show the 218/23 as different colours on the same task bar. I can
create two lines one of 218 and one of 23, change the colour on both and then
link them together, but ideally I'd like to have them on one line as I have a
number of tasks with splits in this way!
Much thanks in advance
Dek