formatting dates

C

CC

For the following formula,

=IF(A1="","",A1+1)

note: where A1 is a start date

How do I format it for weekdays only?

I'm trying to create a schedule template that will work backwards.

Thanks in advance for your help.
 
T

Trevor Shuttleworth

One way:

=IF(A1="","",A1+IF(OR(WEEKDAY(A1)=6,WEEKDAY(A1)=7),3,1))

Regards

Trevor
 
R

Ron Coderre

If you want to list consecutive workdays, beginning with the value in A1, try
this:

A1: (StartDate)
A2: =IF(A1="","",A1+MATCH(TRUE,(WEEKDAY(A1+{1,2,3},2)<6),0))
Copy A2 down as far as you need

Does that help?
***********
Regards,
Ron

XL2002, WinXP
 
D

Daniel CHEN

Custom formatting as "dddd".
Your results will be shown as Monday, Tuesday, etc.

--
Best regards,
---
Yongjun CHEN
=================================
XLDataSoft - Data Analysis Expert, Excel/VBA Specialist
- - - - www.XLDataSoft.com - - - -
Free Excel-Based Data Processing Tool is Available for Download
Free Excel / VBA Training Materials is Available for Download
=================================
 
S

Sandy Mann

Just another way:

=IF(A1="","",A1+3^(WEEKDAY(A1,2)>=5))

If A1 will always be a weekday then it can be slightly shortened to:

=IF(A1="","",A1+3^(WEEKDAY(A1,2)=5))

--
HTH

Sandy
In Perth, the ancient capital of Scotland

[email protected]
[email protected] with @tiscali.co.uk
 
R

Ron Coderre

Another way...a bit more compact:

For A1 = any StartDate (even a Sat or Sun)

A2: =A1+MATCH(MAX(WEEKDAY(A1+1,2),5),{5,7,6},0)
Copy A2 down as far as needed

***********
Regards,
Ron

XL2002, WinXP
 
D

Dave Peterson

If you have the analysis toolpak loaded (tools|Addins), you can use a range that
contains that list of holidays (give it a nice name):

=IF(A1="","",WORKDAY(A1,1,holidays))
 
G

GregR

Dave, thanks again

Greg
Dave said:
If you have the analysis toolpak loaded (tools|Addins), you can use a range that
contains that list of holidays (give it a nice name):

=IF(A1="","",WORKDAY(A1,1,holidays))
 
C

CC

Hi Dave.....I tried your formula (a form of it), but I am still getting an
error:

=IF($E$42="","",WORKDAY($E$42+I11))

E42 is the start date and I11, I12, etc. are the cells that I have set aside
to adjust the amount of days I am working back. So for example, if E42 is
Monday July 10, I want the date above to be Friday July 7 (so I set I11 to be
-1).

FYI, I checked the analysis toolpak and analysis toolpak vba in the add-ins.

Any help is appreciated. Thanks! -CC
 
R

Ron Coderre

Try this:

=IF($E$42="","",WORKDAY($E$42,I11))

Notice the comma in the WORKDAY section of the formula. The second argument
of the WORKDAY function is for the number of workdays to be added/subtracted.

Does that help?
***********
Regards,
Ron

XL2002, WinXP
 
C

CC

SUCCESS! Thanks Ron. -CC

Ron Coderre said:
Try this:

=IF($E$42="","",WORKDAY($E$42,I11))

Notice the comma in the WORKDAY section of the formula. The second argument
of the WORKDAY function is for the number of workdays to be added/subtracted.

Does that help?
***********
Regards,
Ron

XL2002, WinXP
 
R

Ron Coderre

You're welcome....(but, Dave Peterson deserves the credit.)

***********
Regards,
Ron

XL2002, WinXP
 