G
Guest
I have a resource who only works Thursdays & Fridays, and when I switch
to a bar rollup view for my project, the task bars for her work have a
glitch: if an individual task takes more than 2 days for her to
complete, the task bar in question spans non-working days for her.
For example, if a task for her starts on Thursday, May 12 and requires
20 hours of her time, it should take her May 12, 13 and part of May 19
to complete. However, in the bar rollup view, the task bar spans May
12, 13, 14, 15, 16, 17, 18 and 19.
How can I make the bar not show up for May 14-18? When I present this
output to management, it makes it look like she's working 7 days a
week, and I can't find the answer to this anywhere in the task bar
formatting box or Project help.
I'm on MS Project Pro 2003 for Windows. Thanks for any help you can
provide.
to a bar rollup view for my project, the task bars for her work have a
glitch: if an individual task takes more than 2 days for her to
complete, the task bar in question spans non-working days for her.
For example, if a task for her starts on Thursday, May 12 and requires
20 hours of her time, it should take her May 12, 13 and part of May 19
to complete. However, in the bar rollup view, the task bar spans May
12, 13, 14, 15, 16, 17, 18 and 19.
How can I make the bar not show up for May 14-18? When I present this
output to management, it makes it look like she's working 7 days a
week, and I can't find the answer to this anywhere in the task bar
formatting box or Project help.
I'm on MS Project Pro 2003 for Windows. Thanks for any help you can
provide.