S
Simon Williams
Can someone tell me how to format the sumamry roll-up? I need to
replace the std black line with a line reflecting the colours of
various subtasks. So, if I have these tasks represented by the
following colours...
Rqts...Red
Design...Blue
Build...Green
Test...Yellow
I would want a committee to be able to look at a one line entry in the
project file and see how long each phase lasted. So, in text (!)
Red-------Blue------------Green-------------Yellow---
The key thing is this needs to be in one line as I do not want the
summary tasks expanded, but I do want the duration of each task to be
shown.
I can send a screenshot if that helps anyone.
S>
replace the std black line with a line reflecting the colours of
various subtasks. So, if I have these tasks represented by the
following colours...
Rqts...Red
Design...Blue
Build...Green
Test...Yellow
I would want a committee to be able to look at a one line entry in the
project file and see how long each phase lasted. So, in text (!)
Red-------Blue------------Green-------------Yellow---
The key thing is this needs to be in one line as I do not want the
summary tasks expanded, but I do want the duration of each task to be
shown.
I can send a screenshot if that helps anyone.