Trying to calculate this in Excel
I have 3 different processes for an order:
Filling - 300 parts per hour
Packing - 100 parts per hour
Shipping - 50 parts per hour
If I need to staff for 9,000 parts per day for a 7.5 hour day, how would I
calculated my total production for all 3 steps combined per hour remembering
that each part must pass all 3 stations?
I have 3 different processes for an order:
Filling - 300 parts per hour
Packing - 100 parts per hour
Shipping - 50 parts per hour
If I need to staff for 9,000 parts per day for a 7.5 hour day, how would I
calculated my total production for all 3 steps combined per hour remembering