J
James from Sage
Hi,
I made some changes to a project schedule and then Published it back to the
server.
The next time I opened the project file from the server, one of the tasks
had it's work field changed from 102 hrs to 101.98. Nothing about that task
or it's predecessors had been changed the last time I was in that schedule.
Is this a known issue?
Thanks,
- James
I made some changes to a project schedule and then Published it back to the
server.
The next time I opened the project file from the server, one of the tasks
had it's work field changed from 102 hrs to 101.98. Nothing about that task
or it's predecessors had been changed the last time I was in that schedule.
Is this a known issue?
Thanks,
- James