Hi,
for several weeks I was trying to get the full path of a task within
the Resource Usage panel. Finally I found this comment right here:
http://www.tech-archive.net/Archive/Project/microsoft.public.project/2009-02/msg01177.html
My problem is solved in some project plans now. Combining "Summary
Name" and "Copy Task Path" is exactly what I was looking for.
But now I have another problem: this does NOT work in a Resource Pool.
Can you tell me how to solve this problem? How can you display the
whole path of a task within the Resource Usage View within a Resource
Pool? I am using Project 2003. Is there an (easier) way do solve this
problem in Project 2007??
Thanks for your help!
uIDt
for several weeks I was trying to get the full path of a task within
the Resource Usage panel. Finally I found this comment right here:
http://www.tech-archive.net/Archive/Project/microsoft.public.project/2009-02/msg01177.html
My problem is solved in some project plans now. Combining "Summary
Name" and "Copy Task Path" is exactly what I was looking for.
But now I have another problem: this does NOT work in a Resource Pool.
Can you tell me how to solve this problem? How can you display the
whole path of a task within the Resource Usage View within a Resource
Pool? I am using Project 2003. Is there an (easier) way do solve this
problem in Project 2007??
Thanks for your help!
uIDt