future task already finished, reschedule

C

CBnation

In my planning, I have a task for next week that is already finished
The completion is at 100%. But when doing resource levelling, late
tasks are not shifting forward. How can this be done?

I know how to move unfinished tasks from the past to the future, bu
this is the opposite that I want to achieve.

Thanks,

Cedri
 
J

JulieS

Hello Cedric,

Set the Actual Start date and Actual Finish date for the task that
finished early. Assuming the task has successors, they should shift
automatically.

I hope this helps. Let us know how you get along.

Julie