Gannt View under My Tasks

V

vandermt

Hi,
We are using Project 2007.
Under the My Tasks view we are trying to select Tasks Gannt View by using
the Go To pulldown.
All we are seeing is Tasks Gannt View greyed out.
How do we enable Tasks Gannt View from My Tasks view?
Thanks
 
D

Dale Howard [MVP]

vandermt --

The Project Server administrator needs to enable this option. In PWA, click
Server Settings - Task Settings and Display, and then select the Enable
ActiveX Gantt View for All Users option. Hope this helps.
 
V

vandermt

works great
thanks

Dale Howard said:
vandermt --

The Project Server administrator needs to enable this option. In PWA, click
Server Settings - Task Settings and Display, and then select the Enable
ActiveX Gantt View for All Users option. Hope this helps.
 