T
trailerpup
Quick search ends in no joy....
I had a fellow scheduler drop buy with a question. He has inherited
Project (2003) file. The task bars in the gantt chart view do no
reflect the "start" and "finish" dates in the start and finish column
When the dates are added to each end of the bar in the gantt chart view
the task bar extends from the start date but does not stretch all th
way out the planned finish date. I did a cursory view of the file on m
way out and there was nothing readily apparent that would be drivin
this condition.
I'm new to MS Project (6 months), 10 years OPP, P3. I am stil
discovering some "interesting" things in this software package. I thin
I had something similar happen to me in Artemis where the base-line
resources were taking over the gantt bar.
Do any of my fellow techarena lurkers have any input before I start m
deep dive?
Thanks
I had a fellow scheduler drop buy with a question. He has inherited
Project (2003) file. The task bars in the gantt chart view do no
reflect the "start" and "finish" dates in the start and finish column
When the dates are added to each end of the bar in the gantt chart view
the task bar extends from the start date but does not stretch all th
way out the planned finish date. I did a cursory view of the file on m
way out and there was nothing readily apparent that would be drivin
this condition.
I'm new to MS Project (6 months), 10 years OPP, P3. I am stil
discovering some "interesting" things in this software package. I thin
I had something similar happen to me in Artemis where the base-line
resources were taking over the gantt bar.
Do any of my fellow techarena lurkers have any input before I start m
deep dive?
Thanks