Gantt Chart Duration Column

J

John

Is there a quick and easy way to change the duration column from days into
hours? I'm using a standard calendar where the workday is 8 hours, so I
want to change a task that is 1 day and make Project say 8 hours instead.

John
 
M

Mike Glen

Hi John,

Welcome to the Microsoft Project newsgroup :)

Don't forget to reset to Hours in Tools/Options.../Schedule tab - Duration
is entered in:

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 