C
Chris
Hi,
This is my first time using project and I have been following all the tips
and help lines but there is one I can't seem to fix. I have set my calendar
and I have set the working times and non-working times. I have saved my
calendar and am using the calendar I have saved. I enter my task under the
task name and the duration. The start date is displayed but the finish date
does not represent the number of days I have indicated. The Gantt chart does
not take into account my calendar working and non-working days so with
dedicating only 16 hours per week to this project the calendar shows me
working the standard times which I have changed.
Can you help me show the true times of the project on the gantt chart.
This is my first time using project and I have been following all the tips
and help lines but there is one I can't seem to fix. I have set my calendar
and I have set the working times and non-working times. I have saved my
calendar and am using the calendar I have saved. I enter my task under the
task name and the duration. The start date is displayed but the finish date
does not represent the number of days I have indicated. The Gantt chart does
not take into account my calendar working and non-working days so with
dedicating only 16 hours per week to this project the calendar shows me
working the standard times which I have changed.
Can you help me show the true times of the project on the gantt chart.