Gantt chart question

K

kellycell

On my gantt chart in the project plan, I have months on the top tier an
weeks on the bottom tier. My gantt starts the tasks on Month 2, althoug
it should start them on Month 1.
How can I fix that?
Many thanks
 
J

JulieS

Hi kellycell,

The Gantt chart format that you've selected normally starts from the
start date of the project. It sounds from your description that
your project start date is before the start date of the first task.
Check Project > Project Information and confirm your project start
date.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 