gantt charts on master and sub projects

L

Little Elvis

Is it possible to have a master project with sub projects and chart each of
the stages of the subprojects on a single line - using different colours or
symbols for each stage.
So you would have
time line
| | | | | | | | | | | |
Project1 ----------xxxxxwwwwwoooooooCCCCC
Project2 ------xxxxxxxxxxxxxwwooooooCCC

etc..

I'm using project 2000 and can't see a way of doing this.

Thanks.
 
J

JulieS

Hi Little Elvis,

As far as I know there is no way to change colors for only part of a task.
Sorry.

I hope this helps. Let us know how you get along.

Julie
 
J

John

Elvis said:
Can I have the colours change for summary tasks at least. BUt still have them
on a single line.

Elvis,
Pardon me for jumping in here. This question has been asked at various
time in the past in this newsgroup. The good news is, there are various
ways to do what I think you want but it will take some setting up. But
rather than good through all the details again, I suggest you do a
search in this newsgroup. I did a quick check and one past post that
might help get you started was titled, "Multi-colored rollup bars" and
posted 7/28/04.

Hope this helps.
John