G
Gina
Hi,
My problem is that in the timescale of my Gantt chart, I have month 1, 2, 3
etc instead of dates as this my project is generic. I would like my project
to start in July and consequently, i would like July to be month 1 (not month
2 as it shows at present) Is there any way I can change the timescale so that
the timescale starts from month one (july) and not month -1 (may)
My problem is that in the timescale of my Gantt chart, I have month 1, 2, 3
etc instead of dates as this my project is generic. I would like my project
to start in July and consequently, i would like July to be month 1 (not month
2 as it shows at present) Is there any way I can change the timescale so that
the timescale starts from month one (july) and not month -1 (may)