Hi Chris,
This sounds like a fiscal date setting, the subject of our first FAQ.
You
might like to see FAQ Item: 1. on fiscal dates at this web address:
http://project.mvps.org/faqs.htm
1. Strange Dates in Gantt? Check the Fiscal Year
In Tools > Options > Calendar there is a setting for Fiscal year
starts in:
This is to align the Gantt calendar with that required by the
accountants.
Setting it to other than January will change the year at the fiscal
changeover month. For example, if September is the beginning of the
fiscal
year, then August 2000 will change over to September 2001 at midnight
on
August 31st 2000. You are advised to use January most of the time,
change to
your fiscal year to view or report fiscal matters and then change it
back to
January. [Fiscal year can be shown on the timescales in Project
2000.]
Hope this helps - please let us know how you get on
Mike
See
http://tinyurl.com/2xbhc for my free Project Tutorials
The Gantt Chart timescale reads 2009 while my Start and Finish dates
are in 2008.
Is there a fix for this?
Chris