T
Tim
I want to load a resource on a project that is always
dedicated 4 hrs day to that task within that project. No
matter what that resource fills in the actual work field,
I always want 4 hrs a day scheduled for that resource on
that task. How should I go about doing this?
Thank you,
Tim
dedicated 4 hrs day to that task within that project. No
matter what that resource fills in the actual work field,
I always want 4 hrs a day scheduled for that resource on
that task. How should I go about doing this?
Thank you,
Tim