M
Mike Project User
i'm new to Microsoft Project. i can see that Project is very powerful, but
i have a bunch of questions.
as a project manager i find it really confusing that MSP schedules tasks
weeks or months past the date i've set for "Finish No Later Than". i
expected to be able to tell MSP when project needs to be completed by and
give it a list of prioritized tasks and resources. i expected MSP to then
highlight in red which of the tasks wouldn't be completed in time or to tell
me how many resources i would need to get it done by that time. is there
some way to do this?
if i increase the priority of a task, shouldn't it start earlier than those
with a lower priority?
i added the status indicator column. on a couple of tasks i saw it said
"this assignment work has been edited" what does that mean? also, when i
added this column the status indicator indicates that the task is complete
(even though the complete % is set to 0). regular blue (information)
indicator does not indicate the task is complete
what are the dates in the task information screen? why/when would set
these? how is this different from setting constraints?
thanks
i have a bunch of questions.
as a project manager i find it really confusing that MSP schedules tasks
weeks or months past the date i've set for "Finish No Later Than". i
expected to be able to tell MSP when project needs to be completed by and
give it a list of prioritized tasks and resources. i expected MSP to then
highlight in red which of the tasks wouldn't be completed in time or to tell
me how many resources i would need to get it done by that time. is there
some way to do this?
if i increase the priority of a task, shouldn't it start earlier than those
with a lower priority?
i added the status indicator column. on a couple of tasks i saw it said
"this assignment work has been edited" what does that mean? also, when i
added this column the status indicator indicates that the task is complete
(even though the complete % is set to 0). regular blue (information)
indicator does not indicate the task is complete
what are the dates in the task information screen? why/when would set
these? how is this different from setting constraints?
thanks