When a TM views thier activities, is there a way they can see when the last
update was made? The last published schedule?
 
D

Dale Howard [MVP]

Marc --

The default Timesheet page contains the Submitted On column which shows the
latest date for which actuals were submitted for each task. Does this
information meet the needs of your team members, or is there something else
they need to see? Let us know.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 