Generate Weekly Schedule for each Resource

  • Thread starter Background image only on first page?
  • Start date
B

Background image only on first page?

Hi there,

How can a generate a weekly schedule for each of my resources, so for each
calendar week, they can see what they are doing each day? Thank you.
 
G

Gérard Ducouret

Hi,

In the Gantt Chart, combine the "Date Range" filter, and an automatic filter
(Autofilter) in the Resource Name column
Hope this helps,

Gérard Ducouret

"Background image only on first page?"
 
B

Background image only on first page?

Hi Gérard,

Thank you for your reply. I should have been a little more specific as to
what I am looking to do. My resources have tasks, some of which are linked to
each other (Mainly, a developer's task and a proofreader's task. While I want
to generate a weekly to do list for the developer, I would still like them to
know who their proofreader is.)

My team does not have MS Project, so I need to communicate to them what they
are doing and when, on a weekly basis.

For example, I would like to be able to generate something like this for
each user:

Week of March 12
Developer - Task Name - Start Date - Finish Date - Duration
Proofreader - Task Name - Start Date - Finish Date - Duration
Developer - Task Name - Start Date - Finish Date - Duration

Week of March 19
Developer - Task Name - Start Date - Finish Date - Duration
Proofreader2 - Task Name - Start Date - Finish Date - Duration
Developer - Task Name - Start Date - Finish Date - Duration

Can MS Project generate this information organized by calendar week? All of
the information is in MS Project, but I have not been able to find a report
or any way to organize the information like the above.

Thanks!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top