Base calendar interaction with a resource calendar

Discussion in 'Project' started by Lancer, Dec 29, 2017.

  1. Lancer

    Lancer

    Joined:
    Dec 29, 2017
    Messages:
    1
    Likes Received:
    0
    I am using MSP 2013. I set up my project with a 24hr calendar and have adjusted the Project Options/Schedule/Defaults to reflect that.

    I have created resources with dedicated calendars of 8hr and/or 10hr. When i assign resources the applicable resource calendar should be initiated for that task. How can i verify that?

    I am having issues with the resource calendar not displacing the project calendar when i assign the resources.

    When i go to Task Information/Advanced/Calendar the applied resource calendar does not show. i get either 24hr or none in the Task Information/Advanced/Calendar cell.

    Do i have to manually set the calendar for each task using the Task Information/Advanced/Calendar?
     
    Lancer, Dec 29, 2017
    #1
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.