get who doesn't do the task report

W

wayan

Hi, i need to know how to get a report of:
how many overdue tasks in total of the assigned resources that he dont update.
thanks in advance
 
J

John

wayan said:
Hi, i need to know how to get a report of:
how many overdue tasks in total of the assigned resources that he dont update.
thanks in advance

wayan,
For starters, try the Resource Usage view and apply the "Splipped/Late
Progress" filter.

John
Project MVP
 