Actually Project will and should adjust both as you adjust the resources.
Since the cost is principally the labour costs, the cost of a task requiring
20 man-hours will have to be different from the cost of a task requiring 40
man-hours. And since work drives the duration, adjusting resources will
also adjust the duration. You seem to be saying you want to change the
resource assignments and while the duration changes in response, the cost
wouldn't. How could that possibly happen in the real world?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
Bigjim said:
Reasonabley new to project and am bastarising a shedule for a mine. I
want
to be able change resources and have the duration adjusted not the cost.
Any
ideas how I can do this.
thanks