I have a project managing the production of lots of machined parts, each with
several tasks involved during the production process. I need to get the parts
to finish based on a priority like 1 thru 10. Any one know how I can
accomplish this other than manually setting constraints or linking them???
 
J

Jan De Messemaeker

Hi BG,

Assign the required resources to the tasks.
Set thje capacity (Max. Units) or the resources
Set a priority (Priority Field) for each task
Tools, Resource Leveling.