Global Resource Template

R

Rob

If I have gone into a single Resources calendar through the Resource Pool and
have given the resource off lets say the first week of December.
Then if I make changes to the Global Calendar [Standard] after the fact will
it wipe out the first week of December as being off if the Standard Calender
says those are work days.

What is overwritten and what is not.

Luv the EMP Learing books but couldn't find it in here......
 
R

Rod Gill

Hi,

What's in the Standard calendar is the default for all resources using it
(change the base calendar column in the Resource Sheet to use a different
calendar). Any edits in a Resource calendar over-rule anything in the
Standard calendar. Reset a Resource calendar day to Default and the Standard
calendar takes over again.

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: http://www.projectvbabook.com
 