Can anyone tell me how to correct this formula so it does not show #error if
the baseline has not been saved yet? Any help would be greatly appreciated.
Switch(ProjDateDiff([Baseline
Finish],[Finish])/480>=30,2,ProjDateDiff([Baseline
Finish],[Finish])/480>=10,1,True,0)
Thanks
Wendy
the baseline has not been saved yet? Any help would be greatly appreciated.
Switch(ProjDateDiff([Baseline
Finish],[Finish])/480>=30,2,ProjDateDiff([Baseline
Finish],[Finish])/480>=10,1,True,0)
Thanks
Wendy