G
Glenn H
Hi
I have a need to assess how many personnel I need on a daily basis for a project
We don't have the actual personnel as yet but we do have position names. The objective is to
1/ Determine the quantity of personnel needed
2/ Determine the type of personnel needed (ie, Programmer, Hardware Engineer, etc), an
3/ Graph this on a daily basis to forecast how many full time personnel we would need as opposed to part-time/contract personnel
This is also needed for management briefs
I was looking at ways to achieve this via some of the resource views and export it to Excel for the graphing - but have had no luck - as I'm new to Project does anyone have any direction(s) on this one?
I have a need to assess how many personnel I need on a daily basis for a project
We don't have the actual personnel as yet but we do have position names. The objective is to
1/ Determine the quantity of personnel needed
2/ Determine the type of personnel needed (ie, Programmer, Hardware Engineer, etc), an
3/ Graph this on a daily basis to forecast how many full time personnel we would need as opposed to part-time/contract personnel
This is also needed for management briefs
I was looking at ways to achieve this via some of the resource views and export it to Excel for the graphing - but have had no luck - as I'm new to Project does anyone have any direction(s) on this one?