A
Atenoriob
We are trying to implement a central resource pool for our projects using
MS-Project 2003 Standard. The problem we are currently facing is that
Department personnel will be managed using a central resource pool in a
separate file, while material and external resources specific to each project
must be planned individually (locally) in each project file. Given the
material volume each project handles, if it were to be entered in the central
resource pool, it would become an unmanageable monster file.
Up no now the only way we have found for sharing resources between files has
been Tools ïƒ Resource Sharing ïƒ Share Resources ïƒ Use Resources from
FILE.mpp. This option does not allow for a combination of local & central
resource management. Is there a way of accomplishing a dual solution?
Thanks in advance.
MS-Project 2003 Standard. The problem we are currently facing is that
Department personnel will be managed using a central resource pool in a
separate file, while material and external resources specific to each project
must be planned individually (locally) in each project file. Given the
material volume each project handles, if it were to be entered in the central
resource pool, it would become an unmanageable monster file.
Up no now the only way we have found for sharing resources between files has
been Tools ïƒ Resource Sharing ïƒ Share Resources ïƒ Use Resources from
FILE.mpp. This option does not allow for a combination of local & central
resource management. Is there a way of accomplishing a dual solution?
Thanks in advance.