group tasks for reporting purposes

J

Jtighe

I need to group tasks into service blocks for reporting purposes. My customer
is looking to see percentage done against the service block. I have the plan
broken down into a contract description which in some case crosses several
service blocks. I would love to speak with someone on this issue. I aam
fairly certain it can be done I just don't know how. I am using MPP 2003.
Thank you.
 
J

John

Jtighe said:
I need to group tasks into service blocks for reporting purposes. My customer
is looking to see percentage done against the service block. I have the plan
broken down into a contract description which in some case crosses several
service blocks. I would love to speak with someone on this issue. I aam
fairly certain it can be done I just don't know how. I am using MPP 2003.
Thank you.

Jtighe,
I guess the first question is, how are the service blocks identified?
They apparently don't follow the contract WBS (I assume that's what you
mean by "contract description"). If there is a spare field that is used
to identify service blocks, you may be able to get what you need by
using the grouping function found under the Project menu (Project/Group
By/Customize Group By).

If the grouping function doesn't quite get you there, a little more
explanation about the relationship between service blocks and your
contract descriptions, will help us help you. Also, what exactly does
the customer mean by "percentage done"?

John
Project MVP
 