S
Shyler
I am fairly new to MS Project and have been asked to set up a simple project
plan using MS Project 2003. We charge our customers based on the level of
effort it takes to complete the project; we have more than 75 projects with 3
subtasks for each project to track. With that said, it is important we track
completion of the tasks and the cost associated with each task so we provide
the correct budget/fee to our customers. I am struggling with 1) how to
automatically generate dates for two tasks based on a specific start/stop
date of the third task, and (2) which task type to use for resources.
Here are the details of how we operate: each project has 3 subtasks
(planning, execution, and reporting). All the tasks revolve around the start
and stop date of the execution task. Our customers tell us the date for
starting and stopping the Execution task. The Planning task occurs 60
calendar days prior to Execution start and the Reporting task must be
completed 30 calendar days after Execution stop. I attempted to set “must
finish on†and “start no earlier than†constraints but it just isn’t working
out as I planned. Any recommendations for how to automatically generate a
Planning and Reporting task 60 days prior to execution start and 30 days
after execution stop, respectively, for the two tasks? We really don't want
to compute and manually enter dates for all three tasks.
Additionally, resources (people) are assigned as follows for each task:
planning – each person assigned works 35% of their day on this task for the
60 days; execution – each person assigned works 100% of their 8-hour day on
this task; reporting – each person assigned works 35% of their day on this
task for 30 days. No matter what the %, we must calculate 60 days for
Planning, 30 days for Reporting, and x days for Execution (x is provided by
our customer). So here is what I am looking for: I have a 16-hour task and
2 people working @ 100% each, that would be 16 man-hours each for a total of
32 man-hours of work for this one task. So, should this be a task type of
Fixed Duration marked as non-effort driven??
Appreciate any advice.
Thanks,
plan using MS Project 2003. We charge our customers based on the level of
effort it takes to complete the project; we have more than 75 projects with 3
subtasks for each project to track. With that said, it is important we track
completion of the tasks and the cost associated with each task so we provide
the correct budget/fee to our customers. I am struggling with 1) how to
automatically generate dates for two tasks based on a specific start/stop
date of the third task, and (2) which task type to use for resources.
Here are the details of how we operate: each project has 3 subtasks
(planning, execution, and reporting). All the tasks revolve around the start
and stop date of the execution task. Our customers tell us the date for
starting and stopping the Execution task. The Planning task occurs 60
calendar days prior to Execution start and the Reporting task must be
completed 30 calendar days after Execution stop. I attempted to set “must
finish on†and “start no earlier than†constraints but it just isn’t working
out as I planned. Any recommendations for how to automatically generate a
Planning and Reporting task 60 days prior to execution start and 30 days
after execution stop, respectively, for the two tasks? We really don't want
to compute and manually enter dates for all three tasks.
Additionally, resources (people) are assigned as follows for each task:
planning – each person assigned works 35% of their day on this task for the
60 days; execution – each person assigned works 100% of their 8-hour day on
this task; reporting – each person assigned works 35% of their day on this
task for 30 days. No matter what the %, we must calculate 60 days for
Planning, 30 days for Reporting, and x days for Execution (x is provided by
our customer). So here is what I am looking for: I have a 16-hour task and
2 people working @ 100% each, that would be 16 man-hours each for a total of
32 man-hours of work for this one task. So, should this be a task type of
Fixed Duration marked as non-effort driven??
Appreciate any advice.
Thanks,