Grouping in Project Center 2007

R

Robert

Hi,
I have a custom enterprise project field named Region:
Europe
Great Britain
Germany
France
USA
California
Nevada
Arizona

In the Project Center, I can get the total Work (or Cost) for Germany, for
California... but I would like to have also the total at the upper level :
Europe, USA....
How can i do that ?
Thanks
 
M

Marc Soester [MVP]

Hi Robert,

when you groub by your curstom field in the Project Center, you should be
able to see also the first level group ( Europe etc). If this is not the
case, your view was set up to only display the second level of the custom
field. You are able to change this view under server settings > Manage Views.

Hope this helps
 
R

Robert

Marc,
I spoke too fast ;-((
That way, the system displays only the level 1 but it does not sum up any
data at this level ;-((
Anay other idea ?
 
M

Marc Soester [MVP]

Hi Robert,

I have checked it on mine and it does sum up. CAn you tell me what figures
you would like to have summed up? Also check if Cost etc is actually summed up
Thanks
--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
 
M

Mike Mahoney

Hi Robert,

I have checked it on mine and it does sum up. CAn you tell me what figures
you would like to have summed up? Also check if Cost etc is actually summed up
Thanks
--
Marc Soester [MVP]
National Manager: EPMhttp://marcsoester.blogspot.com






- Show quoted text -

Robert

If you are using PS2007 you need to apply SP1 for this functionality.

regards

Mike
 
R

Robert

Thanks Mike,
I'll try to install this SP1...

"Mike Mahoney" <[email protected]> a écrit dans le message de bb90a47b-b3a7-47a7-8584-8b8a715f7515@t66g2000hsf.googlegroups.com...
Hi Robert,

I have checked it on mine and it does sum up. CAn you tell me what figures
you would like to have summed up? Also check if Cost etc is actually
summed up
Thanks
--
Marc Soester [MVP]
National Manager: EPMhttp://marcsoester.blogspot.com






- Show quoted text -

Robert

If you are using PS2007 you need to apply SP1 for this functionality.

regards

Mike
 
M

Mike Mahoney

Hi Robert,

please install SP1, but this functionality that you are after does not
require SP1.
--
Marc Soester [MVP]
National Manager: EPMhttp://marcsoester.blogspot.com






- Show quoted text -

Marc

SP1 provides a new activeX control which enables hierarchical codes to
behave as they did in PS2003, i.e indenting and summarising for each
level of the hierarchy. Pre SP1 does not group in this manner.

regards

Mike
 
R

Robert

Hi Marc,

So what have I to do to get the Total work for Europe and for USA, as well
as the detailed statistics for France, Germany.... in the Project Center ?
 
M

Marc Soester [MVP]

Hi Robert,

in my oppinion you should see this already, but I cannot test this at this
stage since I only have SP1 instances here. Mike suggests that you will have
to install SP1. Try this out and see if it updates the values. From my
understanding it should do this outomatically.
Let me know how you went after SP1 upgrade
Thanks
--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
 