Grouping resources

K

Karen

Hi,

Is there a way of grouping resources and assigning groups to tasks rather
than individuals but still allowing the individuals to book time to the task?
Does that make sense??

Thanks!!
 
C

Chris Marriott

Hi

The scenario you have described will not work

Only the resource you physically assign to the task can book time against it

You could conisder the use of generic resources to represents groups or
roles prior to assigning named resources


--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 
C

Chris Marriott

Karen

Unfortunately not

Only the resource assigned to the task can record time against it

You might consider using Generic Resources to represent groups of users
until you know named resources

Hope this helps some
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 