I'm using MS Project Professional 2002. I have set up outline codes
for tasks, with summary tasks. I would like to do a filter on
'summary tasks' to hide the tasks, and then show a progress bar down
the center of the 'group by summary' on the gantt chart. By changing
the regular looking progress bar to that of a task bar - I could
convey lots of information without the detail. (My customer doesn't
like the dependency lines anyway)
For the progress line, I set the options to: Group by Summary and
actual start --- Complete Through
Nothing happens, is there some way to do this? I've tried the
progress bar before and after the main summary bar to no avail.
Jan
for tasks, with summary tasks. I would like to do a filter on
'summary tasks' to hide the tasks, and then show a progress bar down
the center of the 'group by summary' on the gantt chart. By changing
the regular looking progress bar to that of a task bar - I could
convey lots of information without the detail. (My customer doesn't
like the dependency lines anyway)
For the progress line, I set the options to: Group by Summary and
actual start --- Complete Through
Nothing happens, is there some way to do this? I've tried the
progress bar before and after the main summary bar to no avail.