T
TWS-FoMoCo
We are looking to manage multiple projects through a work team using MS
Project. All projects have been entered into one MS Project database. Our
question is how to use the resources to get a required head count for each
day.
I'm thinking of assigning "dummy" resources" to each task in a single
project. In some cases, multiple resources for a task. Then copy-past the
project for each additional project and then adjust the time.
I'm stuck on how to sum up the number of "heads" required for each day. If
the same resource is assigned to two projects at 100% on the same day, the
summary should say 2 heads required.
Project. All projects have been entered into one MS Project database. Our
question is how to use the resources to get a required head count for each
day.
I'm thinking of assigning "dummy" resources" to each task in a single
project. In some cases, multiple resources for a task. Then copy-past the
project for each additional project and then adjust the time.
I'm stuck on how to sum up the number of "heads" required for each day. If
the same resource is assigned to two projects at 100% on the same day, the
summary should say 2 heads required.