H
Howard Silver
I seem to be having a problem with my team members
entering in their time on their tasks using the web
interface.
When they change the view to "weeks" and enter in their
time for the week, the time they enter in gets spread out
equally across each day in the week.
That I expected!
So for example, for a 40 hour task I would have expected
that 8 hours be allocated for each day Monday through
Friday, and Saturday and Sunday be empty since they have
been defined in the calendar as non-work days.
That is NOT what is happening. It is spreading the 40
hours over all 7 days, giving each day 5.71 hours. THIS
IS WRONG!
How do I force the web interface to recognize non-work
days?
Thanks!
- Howard Silver
entering in their time on their tasks using the web
interface.
When they change the view to "weeks" and enter in their
time for the week, the time they enter in gets spread out
equally across each day in the week.
That I expected!
So for example, for a 40 hour task I would have expected
that 8 hours be allocated for each day Monday through
Friday, and Saturday and Sunday be empty since they have
been defined in the calendar as non-work days.
That is NOT what is happening. It is spreading the 40
hours over all 7 days, giving each day 5.71 hours. THIS
IS WRONG!
How do I force the web interface to recognize non-work
days?
Thanks!
- Howard Silver