M
Marten
I have problem changeing the resource calendar in the enterprise
resource pool. All resources got the "Standard" calendar as base
calendar. I check out one or more resources from the resource pool.
Then I go to "change working time" and select some days and make them
noneworking time. I click save and everything looks good so far. After
that I close the resources and reopen them to check if the changes was
saved. The said part is that they dont take effect.
If their is anyone whit some good suggestions I will be more then
happy to hear from you!
Best regards.
resource pool. All resources got the "Standard" calendar as base
calendar. I check out one or more resources from the resource pool.
Then I go to "change working time" and select some days and make them
noneworking time. I click save and everything looks good so far. After
that I close the resources and reopen them to check if the changes was
saved. The said part is that they dont take effect.
If their is anyone whit some good suggestions I will be more then
happy to hear from you!
Best regards.