I created a customized field with a formula that will provide a graphical
indicator if your baseline finish date varies from your finish date. I first
tried this in a stand alone project plan and it worked fine. I then opened
Enterprise Global and imported the formula and graphical indicators to the
equivalent enterprise field. It is not working with the enterprise field and
I get a "#ERROR" message in the enterprise custom field. Can any one tell me
what I may have done wrong or how I can check what it is giving the error on.
Thanks.