Help- Enterprise Custom Field with Formula Not Working

Y

Yvonne

I created a customized field with a formula that will provide a graphical
indicator if your baseline finish date varies from your finish date. I first
tried this in a stand alone project plan and it worked fine. I then opened
Enterprise Global and imported the formula and graphical indicators to the
equivalent enterprise field. It is not working with the enterprise field and
I get a "#ERROR" message in the enterprise custom field. Can any one tell me
what I may have done wrong or how I can check what it is giving the error on.
Thanks.
 
D

Dale Howard [MVP]

Yvonne --

Open each project and then press the F9 function key to recalculate the
project. Let us know if this takes care of the error message.
 
Y

Yvonne

Dale,
Re-calculating using F9 did work. Thank you for the resolution. If I
create a new project and insert this column from the beginning, will I still
need to do an F9 on the project plan to re-calculate or just on existing
project plans?
 
D

Dale Howard [MVP]

Yvonne --

I believe you only need to do this in existing projects. Hope this helps.
 
Y

Yvonne

Dale,
You are correct. I tested this and the indicators work as expected with a
new project. Thanks again for your help.

Yvonne
 
D

Dale Howard [MVP]

Yvonne --

You are welcome, my friend! :)




Yvonne said:
Dale,
You are correct. I tested this and the indicators work as expected with a
new project. Thanks again for your help.

Yvonne
 
Top