end2end-tha
I am having the problem that Project 2k3 only wants to do resource leveling for some of my (enterprise) resources. I have constructed an example project file, with two resources and two tasks. If I assign one of the resources, Project inserts a delay to prevent overallocation. If I assign the other, the tasks are scheduled for the same day resulting in overallocation. DO anyone have a clue what I could be doing wrong
Best regard
Thomas