HELP Unable to Update

L

Linda

HI,

For some reason i cannot manage to update the task times
etc from my resources. It has always worked before and now
i seem to get an error message stating that it cannot
update to project.

Could anyone suggest fixes or checks i can do to solve
this?

Because i cannot update, times cannot be reflected in
Project server.

Linda
 
B

Bartolini

Hi Linda,

Can you post more details?
What are the steps you are performing and the exact error messages you are
seeing?

~TS
 
G

Guest

I received Task adjusts and as admin i have tried to
update these task changes to the project plan.

When i click update, microsoft project spooler appears
with "DATABASE ERROR (0X80040E114)". I can't seem publish
anything in relation to this project plan.

I thought about deleting it from the project server and re-
importing it. But since there are updates outstanding i
dont know if this is suitable to do so.

Please advise asap
 