Y
Yvonne
I have set up an enterprise resource pool which all projects use at my
company. I have a need to define different work hours for two resource types.
Projects using company resources should be figured on a 6 hr. day;
contractors should be figured at an 8 hr. day. I have created two different
project calendars (one at 6 hrs; one at 8 hrs.) and assigned the appropriate
resource to the appropriate caledar based on their type. This is not working
as MS project is still using the default settings under
tools/options/calendar and changing the duration based on an 8 hr. day. Any
suggestions how I can accomplish this. This is what I would like to see:
Duration: Work Resource
1.25 day 8 hrs. Company Resource
1 day 8 hrs. Contractor Resource
company. I have a need to define different work hours for two resource types.
Projects using company resources should be figured on a 6 hr. day;
contractors should be figured at an 8 hr. day. I have created two different
project calendars (one at 6 hrs; one at 8 hrs.) and assigned the appropriate
resource to the appropriate caledar based on their type. This is not working
as MS project is still using the default settings under
tools/options/calendar and changing the duration based on an 8 hr. day. Any
suggestions how I can accomplish this. This is what I would like to see:
Duration: Work Resource
1.25 day 8 hrs. Company Resource
1 day 8 hrs. Contractor Resource