help with resosurces

E

ehsclem

Hi,

I have a project with 2 assembly lines and different jobs that can ru
on both or just one of the line.
How can I set a "use ressource A _or_ B" button? In other words, if th
project can be run on both lines, I want MS Project to decide which lin
will be more efficient to use.

Thank
 
J

Jack Dahlgren

Project does not make that sort of decision for you. Sorry.
There may be some possibility of customizing project or an add-on which can
help with this, but out of the box it does not assign resources like that.

-Jack Dahlgren
 