D
Darek
I have a "test" project with a few tasks. To two task I
assigned a the same resource - "res". I published project.
Then I decided to remove "res" from the tasks (and I
removed resource from the Team with Build Team from....).
I logged on to Web Acess with "res" account. I went to
Task menu. There were two removed tasks. I hid them.
Now "res" does not participate in the "test" project.
However in Project Center I still can see the "test"
project.
Is there a way to make "test" project non accesible
for "res" ? Does the only way is to manually delete hidden
tasks in project database ?
I really appreciate you help and comments about it. Thanks.
assigned a the same resource - "res". I published project.
Then I decided to remove "res" from the tasks (and I
removed resource from the Team with Build Team from....).
I logged on to Web Acess with "res" account. I went to
Task menu. There were two removed tasks. I hid them.
Now "res" does not participate in the "test" project.
However in Project Center I still can see the "test"
project.
Is there a way to make "test" project non accesible
for "res" ? Does the only way is to manually delete hidden
tasks in project database ?
I really appreciate you help and comments about it. Thanks.