Hide deleted tasks

A

Arturo

Hi al,
When a project manager deletes some tasks, in Project
Server 2002 the resource could hide that tasks, clicking
on Hide button.
In 2003 I don't see that choice, so how can I hide that
kind of tasks?

Any help will be appreciated.

Arturo
 
D

Dale Howard [MVP]

Arturo --

Has your Project Server administrator set the permission for Hide Tasks to
Deny? If not, there should be a Hide button on the toolbar above the
timesheet on each user's View My Tasks page. Hope this helps.
 
A

Arturo

Thank you Dale.
It was our mistake...

Arturo