Hide task dependencies lines

G

Gil

Hi
Is there a way to hide task links (dependencies) lines from the gantt
charts in PWA?
The option exist in Project Professional (Format>Layout..) but I can't
seem to find it in PWA.
Thanks,
Gil
 
D

Dale Howard [MVP]

Gil --

No, there is no way to remove the link lines in the Gantt charts shown in
PWA. Hope this helps.
 