Hide task in an Adminstrative Project

W

Wplater

How or Can you hide a task in an administrative project? I
know how to hide task in a regular project, but is there a
way in the adminstrative project.
 
D

Dale Howard [MVP]

Wplater --

You cannot hide an administrative task on your timesheet. Administrative
tasks are considered nonworking time tasks by the system, and by default,
cannot be hidden.

If you are seeing administrative tasks on your timesheet that are not
relevant to your situation, contact the manager of the administrative
project in which you are assigned and ask him/her to remove you from that
task. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 