H
Harold
Hi,
I have two questions both of which you have probably seen 1000 tim
but here goes
1. I have a statistical worksheet that will have data added during th
year as it comes available, I want to set it up so all total formula
etc are in place but I dont want it to count or display all the zero
for the rest of the year. Is there a way to not count all the zero
(hence thinking that week has happened) until you enter the data fo
the whole worksheet.
2. is it possible for excell to work out the amount of days betwee
two date fields i.e. field 1 =(2 July 2004) field 2 (20 july 2004) = 1
days. I already have the feilds setup as dates.
Thankyo
I have two questions both of which you have probably seen 1000 tim
but here goes
1. I have a statistical worksheet that will have data added during th
year as it comes available, I want to set it up so all total formula
etc are in place but I dont want it to count or display all the zero
for the rest of the year. Is there a way to not count all the zero
(hence thinking that week has happened) until you enter the data fo
the whole worksheet.
2. is it possible for excell to work out the amount of days betwee
two date fields i.e. field 1 =(2 July 2004) field 2 (20 july 2004) = 1
days. I already have the feilds setup as dates.
Thankyo