Hiding Tasks if Predecessor is not 100%

T

tjcervenka

How do you hide a task until it's predecessor is 100% complete? For
instance the predecessor is "Submit to Manager for Approval" and the
successor is "Approve Submitted Plan". I don't want the successor
showing up on the Manager's to do list if it hasn't been submitted and
the Submit task entered as 100% by the submittee....

I'm using 2007 Beta version....

Thanks,

Tom
 
G

Gérard Ducouret

Tom,

I'm afraid it can't be done without any VBA programming...

Gérard Ducouret
 
G

Gary L. Chefetz [MVP]

The best approach is not to publish assignments that you don't want users to
see. As long as assignments are published, they're visible to the user in
either the all tasks view or the current tasks view.
 