Ashley Matteson
I have a project that has mixed some definate task start dates and some with
unknown dates. I am trying to hide the time line graph on those tasks that
do not have a definate start date.
EXAMPLE: PROJECT START DATE = 1 OCT 04
TASK A = 60 Days and starts 1 OCT 04
TASK B = 30 Days but does NOT start 1 OCT 04
Unknown Start
The number of days for Task B is correct WHEN IT IS STARTED. If it show up
on the time line starting 1 OCT 04 like the rest of the tasks then 60 days
later people will ask why it is not done. If I knew a start date I could
select start on and put in the date, but I do not know the date, just the
length. It would be best if I could hide the data from the time line to
avoid confusion.
If anyone has an answer, please post it here and if possible, email me at
[email protected]
THANKS!
unknown dates. I am trying to hide the time line graph on those tasks that
do not have a definate start date.
EXAMPLE: PROJECT START DATE = 1 OCT 04
TASK A = 60 Days and starts 1 OCT 04
TASK B = 30 Days but does NOT start 1 OCT 04
Unknown Start
The number of days for Task B is correct WHEN IT IS STARTED. If it show up
on the time line starting 1 OCT 04 like the rest of the tasks then 60 days
later people will ask why it is not done. If I knew a start date I could
select start on and put in the date, but I do not know the date, just the
length. It would be best if I could hide the data from the time line to
avoid confusion.
If anyone has an answer, please post it here and if possible, email me at
[email protected]
THANKS!