Historical Timesheet Modification

B

Bilbo

Hello,

How can I prevent a resource from modifying historical actuals in their
timessheet. For instance they can currently log in to PWA and modify their
actuals in March 04....but I only want them to modify June 04.

Thanks.
 
D

Dale Howard [MVP]

Bilbo --

If you are using Project Server 2003, you can use managed time periods to
project actuals in past time periods and to prevent users from entering
actuals in future time periods. If you have Project Server 2002, or are not
using managed time periods with Project Server 2003, then you must make this
a training and performance issue with both team members and project
managers. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 