Is there a way to go back and see a report of who has updates tasks in a
project plan? For example, if one of my resources sends me (PM) an update
and I accept - how can I go back to figure out what I accepted? Is there a
way for the resource or the PM to see this?
 
P

/pd

Goto Approval secton = >task updates =>goto=>Reviewed Requests..

...you should get a history of task updates !!
 
J

JoeC

This definitely helps but it is still a bit difficult to see what they did on
the task. For example, if they changed the progress from 25% to 50%, it
really doesnt tell you that. It just says 50%.
 
P

/pd

depends on how PS)7 default are setup... have you taken a look at the other
menu option .. "Review applied request /errors", this has more info
it..along with work remaining stats.. etc
 